Question: Jobs A, B, and C are waiting to be started on machine center X and then be completed on machine center Y. The following information

Jobs A, B, and C are waiting to be started on machine center X and then be completed on machine center Y. The following information pertains to the jobs and work centers.
Hours Allowed for Machine Hours Allowed for Machine Day When Job Center X Center Y Due 36 20 10 96 24 17 60 28 25

Machine center X and machine center Y have 40 hours of capacity per week (5 working days per week eight hours/day). Two days are allowed to move jobs between machine centers.
a. If these jobs are rescheduled by earliest due date. can they be completed on time?
b. Can they be completed on time using the critical ratio technique?
c. Can the jobs be completed on time (using the earliest due date or critical ratio technique) if 20 hours of overtime are run in work center X each week?
d. Can the jobs be completed on time (using the earliest due date or critical ratio technique) if only one day is required between operations?

Hours Allowed for Machine Hours Allowed for Machine Day When Job Center X Center Y Due 36 20 10 96 24 17 60 28 25

Step by Step Solution

3.51 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

A Earliest due date Machine X and Y have a capacity of 40 hours per week And in a week machinery is ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Document Format (1 attachment)

Word file Icon

1019-B-C-F-D-F(1422).docx

120 KBs Word File

Students Have Also Explored These Related Corporate Finance Questions!