Question: A small sample of your projects PERT calculations is shown here. What is the total duration of the project? A. 33 B. 38 C. 37

A small sample of your project’s PERT calculations is shown here. What is the total duration of the project?Activity 1 Optimistic 10 Pessimistic Likely Expected Value 14 12 2 20

A. 33 B. 38 C. 37 D. 47

Activity 1 Optimistic 10 Pessimistic Likely Expected Value 14 12 2 20 30 23 3 3 3 3