Question: The WBS, estimates for each work package, and the network diagram are completed. The NEXT thing for the project manager to do is: A. Sequence
The WBS, estimates for each work package, and the network diagram are completed. The NEXT thing for the project manager to do is: A. Sequence the activities. B. Validate that they have the correct scope. C. Create a preliminary schedule and get the team's approval. D. Complete risk management.