Question: The WBS, estimates for each work package, and the network diagram are completed. The next thing for the project manager to do is: A. Sequence
The WBS, estimates for each work package, and the network diagram are completed. The next thing for the project manager to do is:
A. Sequence the activities B. Validate that they have the correct scope C. Create a preliminary schedule and get the team's approval D. Complete risk management