Question: The WBS , estimates for each work package, and the network diagram are completed. The next thing for the project manager to do is: Question

The WBS, estimates for each work package, and the network diagram are completed. The next thing for the project manager to do is:
Question 23Answer
a.
Validate that they have the correct scope
b.
Complete risk management
c.
Create a preliminary schedule and get the teams approval
d.
Sequence the activities