Question: The WBS , estimates for each work package, and the network diagram are completed. The next thing for the project manager to do is: Question
The WBS estimates for each work package, and the network diagram are completed. The next thing for the project manager to do is:
Question Answer
a
Validate that they have the correct scope
b
Complete risk management
c
Create a preliminary schedule and get the teams approval
d
Sequence the activities