Question: The main Data Analysis Methods used during the Control Schedule Process include the following: A) The Earned-Value Analysis, the Iteration BURNDOWN-CHART, and the Performance Reviews.

The main Data Analysis Methods used during the “Control Schedule” Process include the following:

A) The Earned-Value Analysis, the Iteration BURNDOWN-CHART, and the Performance Reviews.

B) The Trend Analysis, the Variance Analysis, and the What-If Scenario Analysis.

C) Both Options above are Correct.

D) All Options above are Incorrect.

ANSWER: C