Question: Which technique are you using if you are calculating the theoretical early start and finish dates on your project schedule, along with late start and

Which technique are you using if you are calculating the theoretical early start and finish dates on your project schedule, along with late start and finish dates, for all the project activities?

A. Critical chain method B. Critical path method C. Schedule compression D. What-if analysis