Question: A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources is called: A. * Crashing. B. Program

A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources is called:

A. * Crashing.

B. Program evaluation and review technique (PERT).

C. Precedence diagramming method (PDM).

D. Fast tracking.