Question: Crashing in schedule management is: A. * A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources.

”Crashing” in schedule management is:

A. * A schedule compression technique used to shorten the schedule duration for the least incremental cost by adding resources.

B. A schedule compression technique in which phases or activities that are normally done in sequence are performed in parallel.

C. The timely input of data to calculate the critical path.

D. Equivalent to minimizing float in the project schedule network