Question: BAC = 200PV = 100AC = 120EV = 80 Assuming that what the project has experienced to date can be expected to continue in the
BAC = 200PV = 100AC = 120EV = 80 Assuming that what the project has experienced to date can be expected to continue in the future, the variance at completion (VAC) is:
A. -80.
B. * -100. .
C. +100.
D. +200