Question: BAC = 200PV = 100AC = 120EV = 80 Assuming that what the project has experienced to date can be expected to continue in the

BAC = 200PV = 100AC = 120EV = 80 Assuming that what the project has experienced to date can be expected to continue in the future, the variance at completion (VAC) is:

A. -80.

B. * -100. .

C. +100.

D. +200