Question: BAC = 200PV = 100AC = 120EV = 80Assuming that what the project has experienced to date can be expected to continue in the future,
BAC = 200PV = 100AC = 120EV = 80Assuming that what the project has experienced to date can be expected to continue in the future, the estimate at completion (EAC) is:
A. * 300.
B. 325.
C. 350.
D. 375.