Question: BAC = 200PV = 100AC = 120EV = 80Assuming that what the project has experienced to date can be expected to continue in the future,

BAC = 200PV = 100AC = 120EV = 80Assuming that what the project has experienced to date can be expected to continue in the future, the estimate at completion (EAC) is:

A. * 300.

B. 325.

C. 350.

D. 375.