Question: BAC = 200PV = 100AC = 120EV = 80Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC)
BAC = 200PV = 100AC = 120EV = 80Assuming that all future work will be performed at the budgeted rate, the estimate to complete
(ETC) is:
A. * 120.
B. 140 C. 180 D. 200