Question: BAC = 200PV = 100AC = 120EV = 80Assuming that all future work will be performed at the budgeted rate, the estimate to complete (ETC)

BAC = 200PV = 100AC = 120EV = 80Assuming that all future work will be performed at the budgeted rate, the estimate to complete

(ETC) is:

A. * 120.

B. 140 C. 180 D. 200