Question: For an activity with ES = 4, EF = 7, LS = 6, LF = 9, the activity has: (a) Total float of 2 (b)

For an activity with ES = 4, EF = 7, LS = 6, LF = 9, the activity has:

(a) Total float of 2

(b) Free float of 2

(c) Total float of 3

(d) Free float of 3