Question: You are managing a project which is into six months of its execution. You are now reviewing the project status and you have ascertained that

You are managing a project which is into six months of its execution.

You are now reviewing the project status and you have ascertained that project is behind schedule. The actual cost of Activity A is Rs. 2,00,000 and that of Activity B is Rs. 1,00,000. The planned value of these activities are Rs. 1,80,000 and Rs. 80,000 respectively. The Activity A is 100%

complete. However, Activity B is only 75% complete. Calculate the cost performance index of the project on the review date.

A. 0.7 B. * 0.8 C. 0.9 D. 0.6