Question: You are managing a project which is into five months of its execution. You are now reviewing the project status. The actual cost of Activity

You are managing a project which is into five months of its execution. You are now reviewing the project
status. The actual cost of Activity A is 3,00,000 and that of Activity B is 1,50,000. The planned value of
these activities are 2,80,000 and 1,20,000 respectively. The Activity A is 90% complete and Activity B
is only 80% complete. Calculate the schedule performance index and cost performance index of the Project
on the review date. And make comments on the project status.