Question: In a CPM network, the critical path has six activities. Their durations are tabulated next. Duration (Days) Activity Optimistic (To) Most Likely (Tm) Pessimistic (Tp)
In a CPM network, the critical path has six activities. Their durations are tabulated next.
Duration (Days)
Activity Optimistic (To) Most Likely (Tm) Pessimistic (Tp)
B 2 3 5 D 4 8 13 F 5 6 8 K 3 3 3 N 7 10 15 S 3 5 8 Compute the following:
a. The probability that the project will finish by the end of day 36
b. The probability that the project will finish by the end of day 39
c. The probability that the project will finish before day 38
d. The probability that the project will finish on day 35
e. The probability that the project will finish at least 3 days early
f. The probability that the project will finish more than 4 days late g. The completion date with at least a 90% confidence level