Question: Given the following network, (a) What is the critical path? (b) How long will it take to complete this project? Start A8 D7 C3 B10
Given the following network,

(a) What is the critical path?
(b) How long will it take to complete this project?
Start A8 D7 C3 B10 IXI E6 F7 G5 H3 End
Step by Step Solution
3.50 Rating (160 Votes )
There are 3 Steps involved in it
To solve this problem we need to find the critical path and the project duration by analyzing the gi... View full answer