Question: A project is being analyzed with below activities identified. Activities A and B start on day 0. Activity Immediate Predecessors Duration (days) a. organize layout
A project is being analyzed with below activities identified. Activities A and B start on day 0.
| Activity | Immediate Predecessors | Duration (days) |
| a. organize layout team | - | 3 |
| b. organize modification team | - | 6 |
| c. design personnel jobs | a | 6 |
| d. set machinery in place | b | 4 |
| e. connect utilities | c, d | 7 |
| f. modify conveyor system | e | 4 |
| g. train personnel | e | 5 |
| h. finishing touches | f | 4 |
| i. run test lot | g | 3 |
- Find ES, EF, LS, LF, and Slack values all activities.
- What is (are) the critical path(s)?
- What is expected project duration?