Question: A project is being analyzed with below activities identified. Activities A and B start on day 0. Activity Immediate Predecessors Duration (days) a. organize layout

A project is being analyzed with below activities identified. Activities A and B start on day 0.

Activity Immediate Predecessors Duration (days)
a. organize layout team - 3
b. organize modification team - 6
c. design personnel jobs a 6
d. set machinery in place b 4
e. connect utilities c, d 7
f. modify conveyor system e 4
g. train personnel e 5
h. finishing touches f 4
i. run test lot g 3
  1. Find ES, EF, LS, LF, and Slack values all activities.
  2. What is (are) the critical path(s)?
  3. What is expected project duration?

A project is being analyzed with below activities

2 h e 5 LO 3

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!