Question: 1. Consider the folowing project : Activity Precedence Duration A 10 B 15 C B 5 D . 3 E 20 F D, E, G

1. Consider the folowing project : Activity

1. Consider the folowing project : Activity Precedence Duration A 10 B 15 C B 5 D . 3 E 20 F D, E, G 5 G 15 H G 10 a) Draw the project network. b) Determine the critical path of the project and indicate the total duration of the project. Justify all calculations you perform