Question: 1. Develop a network diagram based on above table 2. What is the project duration of this network? CPM Exercise B Task Name Duration (Days)

1. Develop a network diagram based on above table
1. Develop a network diagram based on above table 2. What is the project duration of this network? CPM Exercise B Task Name Duration (Days) A 3 B C D E F G END 7 4 1 6 5 2 Predecessor(s) A(S-S) A,B D C,D E,F G