Question: 1. Develop a network diagram based on the below table 2. What is the project duration of this network? Taskid Duration (Days) Predecessor(s) Relationship 2

1. Develop a network diagram based on the below table 2. What is the project duration of this network? Taskid Duration (Days) Predecessor(s) Relationship 2 6 4 B D E F G 1 3 1 5 1 2 Start Start , C D B B F G EH 1 FS FS SS FS FS FS FS H 1 End
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
