Question: 1. The time for each activity to complete, the possible weeks by which that time can be reduced and the cost per week to decrease

1. The time for each activity to complete, the possible weeks by which that time can be reduced and the cost per week to decrease the activity time. The cost to complete the project in normal time is $12,000 (40%)

1. The time for each activity to complete, the
Activity Duration (wks) Predecessor(s) Crash weeks Crashing cost (possible) per week $580 $620 $550 D $480 D.E $590 UI G A VIA G UI W W W A UI Q UI A A W F NENI SEENNNN-HI I $600 C,G D, H $560 F.I $520 K J. K $410 L $850 K,N $750 O,P