Question: The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate Predecessors A 4 --- B 2 A C

The critical path for the network activities shown below is _____ with duration ______. Activity Duration Immediate Predecessors A 4 --- B 2 A C 7 -- D 6 A E 5 B,C,D a. A-B-D; 12 b. A-B-E; 11 c. C-E; 12 d. A-D-E; 15 e. A-B-C-D-E; 24