Question: (20 points) In a PERT network, you are given the following data with times in weeks. Activity Immediate Predecessors Optimistic Time Most Likely Time Pessimistic

(20 points) In a PERT network, you are given the following data with times in weeks.

Activity

Immediate Predecessors

Optimistic Time

Most Likely Time

Pessimistic Time

A

--

14

16

18

B

--

6

8

10

C

B

11

14

17

D

C

5

7

15

E

A,D

12

15

24

F

E

9

11

13

G

E

9

10

11

H

F, G

5

6

13

a. Draw a PERT/CPM network for the project and use this to determine the expected number of weeks it will take before the project is finished and the standard deviation. On the diagram, indicate the earliest and latest start and finish for each activity in the project. What is the critical path? (15 points).

b. What is the 95% confidence interval of the completion time? (5 points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!