Question: 6) Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E? Activity Expected Activity Time ES EF

6) Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E?

Activity Expected Activity Time ES EF LF
A 5 0
B 18 5
C 13 5
D 3 23
E 10 23
F 4 33 46
G 11 44