Question: Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E? Activity Expected Activity Time ES EF LF

Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E?

Activity Expected Activity Time ES EF LF
A 5 0

B 18 5

C 13 5

D 3 23

E 10 23

F 4 33
46
G 11

44