Question: Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E? Activity Expected Activity Time ES EF LF
Activity E is succeeded by Activity F and Activity G. What is the LF time for Activity E?
| Activity | Expected Activity Time | ES | EF | LF |
| A | 5 | 0 | ||
| B | 18 | 5 | ||
| C | 13 | 5 | ||
| D | 3 | 23 | ||
| E | 10 | 23 | ||
| F | 4 | 33 | 46 | |
| G | 11 | 44 |
Step by Step Solution
3.47 Rating (157 Votes )
There are 3 Steps involved in it
To determine the LF Late Finish time for Activity E we ... View full answer