Question: A 15 B A 5 C A 19 D A 4 E B,C 7 F C,D 25 G F 8 H F 18 I G,H
| A | 15 | |
| B | A | 5 |
| C | A | 19 |
| D | A | 4 |
| E | B,C | 7 |
| F | C,D | 25 |
| G | F | 8 |
| H | F | 18 |
| I | G,H | 16 |
| J | I | 12 |
| A | 15 | |
| B | A | 5 |
| C | A | 19 |
| D | A | 4 |
| E | B,C | 7 |
| F | C,D | 25 |
| G | F | 8 |
| H | F | 18 |
| I | G,H | 16 |
| J | I | 12 |
Using Pert calculate the time for each activity.
draw a network diagram and identify the critical path