Question: A 15 B A 5 C A 19 D A 4 E B,C 7 F C,D 25 G F 8 H F 18 I G,H

A 15
B A 5
C A 19
D A 4
E B,C 7
F C,D 25
G F 8
H F 18
I G,H 16
J I 12
A 15
B A 5
C A 19
D A 4
E B,C 7
F C,D 25
G F 8
H F 18
I G,H 16
J I 12

Using Pert calculate the time for each activity.

draw a network diagram and identify the critical path