Question: Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 2 B A 3 C A 5 D B 4 E

Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 2
B A 3
C A 5
D B 4
E C%media:cm.png% D 7
F D 2
G F 3
H E%media:cm.png% G 7