Question: A local project being analyzed by PERT has 4 2 activities, 1 3 of which are on the critical path. If the estimated time along

A local project being analyzed by PERT has 42 activities, 13 of which are on the critical path. If the estimated time along the ortical path is 105 dirys with a project rariance of 25, what is the probability that the project will be completed in 95 days or more?
A.4.20000
B.0.97725
C.0.34444
D.0.02275
E -0.40000
A local project being analyzed by PERT has 4 2