Question: A project for improving a billing process has the following precedence relationships and activity times: Activity A B D E F OLUI Activity Time (weeks)

A project for improving a billing process has theA project for improving a billing process has the

A project for improving a billing process has the following precedence relationships and activity times: Activity A B D E F OLUI Activity Time (weeks) Immediate Predecessor(s) 5 8 7 11 B, C 11 B D E F, G 4 7 9 b. Calculate the slack for each activity. Which activities are on the critical path? Activity On critical Activity Time (weeks) path? 5 Slack (weeks) B 8 7 D 11 7 E 11 F 4 G 7 H 9