Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 B 8
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 2 | |
| B | 8 | |
| C | 5 | A |
| D | 12 | B, C |
| E | 11 | B |
| F | 4 | D |
| G | 3 | E |
| H | 9 | F, G |
Calculate the slack for each activity. Which activities are on the critical path?
| Activity | Activity Time (weeks) | On critical path? Yes/No | Slack (weeks) |
| A | 2 | ||
| B | 8 | ||
| C | 5 | ||
| D | 12 | ||
| E | 11 | ||
| F | 4 | ||
| G | 3 | ||
| H | 9 |