Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 minus B
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 2 minus B 12 minus C 7 A D 14 B, C E 11 B F 4 D G 6 E H 7 F, G .
Calculate the slack for each activity. Which activities are on the criticalpath?
| Activity | Activity Time (weeks) | On criticalpath? | Slack (weeks) |
| A | 2 |
| nothing |
| B | 12 |
| nothing |
| C | 7 |
| nothing |
| D | 14 |
| nothing |
| E | 11 |
| nothing |
| F | 4 |
| nothing |
| G | 6 |
| nothing |
| H | 7 |
| nothing |