Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 4 B 7

A project for improving a billing process has the following precedence relationships and activity times:

Activity

Activity Time (weeks)

Immediate Predecessor(s)

A

4

B

7

C

8

A

D

12

B, C

E

10

B

F

4

D

G

7

E

H

9

F, G

A project for improving a billing process has the

b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Slack (weeks) A 4 B 7 C 8 D 12 E 10 F 4 G 7 H 9