Question: A project manager is working on a large IT project. During a review for one of the deliverables. a stakeholder raised a concern about the

A project manager is working on a large IT project. During a review for one of the deliverables. a stakeholder raised a concern about the final product.What should the project manager do first?A. Discuss this with the team and put the stakeholder's concern in the issue log.B. Set up a meeting with the sponsor to discuss the details of the deliverable.C. Discuss this with the team and review the project requirements documentation.D. Set up a meeting with the product owner to discuss the stakeholder's concern.
Which option is correct answer?