Question: A project network has the following activity details Activities Predecessors Duration ( Weeks ) A - 6 B A 4 C A 3 D B
A project network has the following activity details
Activities Predecessors DurationWeeks
A
B A
C A
D B C
E B C
F D E
G F
If Activity D is delayed by weeks beyond its estimated duration, which of the following will be true?
Group of answer choices
Activity D will then have slack of one week
Activity E will start to have a slack
Activity D will be on the critical path
Activity G will no longer be on the critical path.