Question: A project network has the following activity details Activities Predecessors Duration ( Weeks ) A - 6 B A 4 C A 3 D B

A project network has the following activity details
Activities Predecessors Duration (Weeks)
A -6
B A 4
C A 3
D B, C 2
E B, C 5
F D, E 4
G F 4
What is the project duration for this example?
Group of answer choices
19 weeks
26 weeks
28 weeks
23 weeks