Question: A project network has the following activity details Activities Predecessors Duration ( Weeks ) A - 6 B A 4 C A 3 D B

A project network has the following activity details
Activities Predecessors Duration(Weeks)
A -6
B A 4
C A 3
D B, C 2
E B, C 5
F D, E 4
G F 4
If Activity D is delayed by 4 weeks beyond its estimated duration, which of the following will be true?
Group of answer choices
Activity D will then have slack of one week
Activity E will start to have a slack
Activity D will be on the critical path
Activity G will no longer be on the critical path.