Question: A project network has the following activity details Activities Predecessors A B D B, C E B, C F DE G F Duration (Weeks) 6

A project network has the following activity
A project network has the following activity
A project network has the following activity details Activities Predecessors A B D B, C E B, C F DE G F Duration (Weeks) 6 4. 3 2 5 4 4 What is the project duration for this example? 19 weeks 26 weeks 28 weeks 23 weeks In the above example, which of the activities below have a non-zero slack? Activity C o Activity D Activity E Activity F