Question: A project network has the following activity details Activities Predecessors Duration Weeks ) A 6 B 4 3 D B , C 2 E B
A project network has the following activity details Activities Predecessors Duration Weeks A B D B C E B C F DE G F In the above example,which of the activities below have a nonzero slack?
Group of answer choices
Activity C
Activity D
Activity E
Activity F