Question: A project network has the following activity details Activities Predecessors Duration Weeks ) A 6 B 4 3 D B , C 2 E B

A project network has the following activity details Activities Predecessors Duration Weeks) A 6 B 43 D B, C 2 E B, C 5 F DE 4 G F 4 In the above example,which of the activities below have a non-zero slack?
Group of answer choices
Activity C
Activity D
Activity E
Activity F