Question: A project network has the following activity details Activities Predecessors Duration Weeks) A 6 B 4 3 D B, C 2 E B, C 5

A project network has the following activity
A project network has the following activity
A project network has the following activity details Activities Predecessors Duration Weeks) A 6 B 4 3 D B, C 2 E B, C 5 F DE 4 G F 4 In the above example, what is the latest finish time for activity C? 10 weeks 9 weeks 15 weeks 6 weeks