Question: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate

A simple CPM network has three activities, A, B, and C.

  • A is an immediate predecessor of B and of C. B is an immediate predecessor of C.
  • The activity durations are A=38, B=24, C=15.

How long will it take to complete the project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer