Question: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate
A simple CPM network has three activities, A, B, and C.
- A is an immediate predecessor of B and of C. B is an immediate predecessor of C.
- The activity durations are A=38, B=24, C=15.
How long will it take to complete the project?