Question: a) The Project Completion time = __ days. b) The Earliest Start time, ES, of Activity G = __ days. c) The Latest Finish time,

a) The Project Completion time = __ days.
b) The Earliest Start time, ES, of Activity G = __ days.
c) The Latest Finish time, LF, of Acitivity C = __ days.
d) The critical activities are = __ (ex. Fill in answer as: ABCD)
** There should be 4 answers. Please answer carefully.