Question: Given is a CPM project network diagram as shown below. A F Start E . End ( B B D Activity day Start 0 A

Given is a CPM project network diagram as shown

Given is a CPM project network diagram as shown below. A F Start E . End ( B B D Activity day Start 0 A 3 B 6 4 D 7 E 8 F 2 H 3 End 0 5 a) The Project Completion time = days. b) The Earliest Start time, ES, of Activity G= days. c) The Latest Finish time, LF, of Acitivity C= days. d) The critical activities are (ex. Fill in answer as: ABCD)