Question: A ) The time to load a starting work part into the production machine in a certain unit production operation = 0 . 4 0

A) The time to load a starting work part into the production machine in a certain unit production operation =0.40min, the actual processing time in the operation =3.10min, and the time to unload the finished part =0.20min. In addition, the tool must be changed every 5 cycles and the tool change time =1.50min. What is the cycle time for the unit operation?