Question: The time to load a starting work part into the production machine in a certain unit production operation = 0 . 4 0 min, the

The time to load a starting work part into the production machine in a certain unit production operation =0.40 min, the actual processing time in the operation =3.10 min, and the time to unload the finished part =0.20 min. In addition, the tool must be changed every 5 cycles and the tool change time =1.50 min. The cycle time for the unit operation is which one of the following?