Question: The time to load a starting work part into the production machine in a certain unit production operation = 0 . 4 0 min, the

The time to load a starting work part into the production machine in a certain unit
production operation =0.40min, the actual processing time in the operation =3.10
min, and the time to unload the finished part =0.20min. In addition, the tool must
be changed every 5 cycles and the tool change time =1.50min. The cycle time for
the unit operation is which one of the following?
(a)3.5min
(b)3.7min
(c)4.0min
(d)4.5min
(e)5.2min
If the initial cost of a production machine including installation is $250,000, and the
planned use of the machine is 2000hryr for 5 years, and the applicable overhead
rate on the equipment is 50%, which one of the following is the corresponding cost
rate of this machine in $hr?
(a) $0.625
(b) $25.00
(c) $37.50
(d) $50.00
(e) $125.00
 The time to load a starting work part into the production

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock