Question: Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 6. Earliest finish time of
Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 6. Earliest finish time of B is 20 and earliest finish time of C is 17. Latest start time of F is 29. Write down the slack for F.