Question: Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 9. Earliest finish time of

Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 9. Earliest finish time of B is 25 and earliest finish time of C is 27. Latest start time of F is 44. Write down the slack for F.