Question: Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 5. Earliest finish time of
Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 5. Earliest finish time of B is 24 and earliest finish time of C is 16. Latest start time of F is 32. Write down the slack for F.