Question: Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 5. Earliest finish time of

Activity D on a CPM network has predecessors B and C, and has successor F. Activity time for D is 5. Earliest finish time of B is 24 and earliest finish time of C is 16. Latest start time of F is 32. Write down the slack for F.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!